3 INSTALLATION
18
OPTIFLEX 1300 C
www.krohne.com 03/2014 - 4000172306 - HB OPTIFLEX 1300 R07 en
3.3 Transport
3.4 Pre-installation requirements
• Make sure that there is sufficient space on all sides.
• Protect the signal converter from direct sunlight. If necessary, install the weather protection
accessory.
• Do not subject the signal converter to heavy vibrations. The devices are tested for vibration
and agree with EN 50178 and IEC 60068-2-6.
Figure 3-2: How to hold the device
Figure 3-3: How to hold the device
1 Remove the converter before you lift the device with a hoist.
2 Wind cable probes greater than 400 mm / 16¨ in diameter.
3 Do not hold the probe when you lift the device.
4 Do not wind the flexible conduit less than 330 mm / 13¨ in diameter.
WARNING!
If you do not lift the device carefully, you can cause damage to the probe.
INFORMATION!
Obey the precautions that follow to make sure that the device is correctly installed.