Installation in tanks containing one liquid and foam
Drill a pressure equalization hole in the stilling well above the maximum level.
Deburr the hole.
If the probe has a counterweight, make sure that there is enough space between the
counterweight and the wall of the stilling well.
Installation in tanks containing more than one liquid
Drill a pressure equalization hole in the stilling well above the maximum level of the top liquid.
Drill more holes along the length of the stilling well. Distance between holes 25 mm / 1¨
(depends on the minimum layer to be measured)
i These holes help the liquids to move freely.
Deburr the holes.
If the probe has a counterweight, make sure that there is enough space between the
counterweight and the wall of the stilling well.
Floating roofs
If the device is for a tank with a floating roof, install it in a stilling well.
Figure 3-18: Installation recommendations for stilling wells
1 Stilling well in tanks containing one liquid
2 Stilling well in tanks containing more than one liquid
3 Air circulation hole
4 Maximum level of the liquid
5 Liquid circulation hole
6 Distance between holes 25 mm/1¨ (depends on the minimum layer to be measured)